15 min readAs of 24 Nov 2026, the Agricultural Marketing Infrastructure (AMI) godown subsidy is not taking new projects. A DA&FW order of 10 June 2025 put AMI in abeyance, and the DMI page shows no order lifting it. NABARD has also told banks that new claims cannot be sent and pending claims may be kept on hold. AMI was a back-ended capital subsidy of 25%, or 33.33% for FPOs, panchayats, women, SC/ST entrepreneurs, PACS and projects in the North East and hills. The rules below are for reference. For a godown now, the open route is the Agriculture Infrastructure Fund (AIF) 3% interest subvention.
What is the AMI scheme?
AMI stands for Agricultural Marketing Infrastructure. It is a sub-scheme of the Integrated Scheme for Agricultural Marketing (ISAM) of the Department of Agriculture and Farmers Welfare (DA&FW). The Directorate of Marketing and Inspection (DMI) runs it. It gives a capital subsidy on godowns, warehouses and some marketing structures, but only if a bank or NCDC finances the project.
The DMI scheme page shows that AMI took over from two older schemes from 1 April 2014: the Grameen Bhandaran Yojana (rural godown scheme) and the scheme for strengthening agricultural marketing infrastructure, grading and standardisation (AMIGS). The subsidy is back ended. The government pays it to your lending bank, half in advance, and the bank adjusts it in your loan account at the end.
Two short terms help later. TFO is Total Financial Outlay, the project cost used in the subsidy sum. WDRA is the Warehousing Development and Regulatory Authority, which registers warehouses. If you want the selling side, see our guides on e-NAM registration and selling and on what to do when the mandi price is below MSP.
Is the AMI scheme giving new subsidy in 2026?
No. As of 24 Nov 2026, new AMI sanctions are on hold. A DA&FW order of 10 June 2025 says the allocated budget is fully used and AMI is kept in abeyance. No new sanction may be made until fresh budget is communicated. The DMI page lists this order as its newest item and shows no order that lifts it.
The DA&FW letter is addressed to the Joint Agricultural Marketing Adviser at DMI and to the Chairman of NABARD. NABARD passed it on to banks in its circular 149 of 10 June 2025. The circular says the ENSURE portal was switched off for new AMI claims. It also says pending claims at all levels may be kept in abeyance until DMI gives further orders. The DMI page lists current circulars as Not Available.
The last continuation letter on that page is the DMI letter of 8 Nov 2021. It kept AMI going from 1 April 2021 to 31 March 2022 or until further order, whichever is earlier. A PIB explainer of 23 March 2026 still describes AMI and gives progress figures up to 31 January 2026, but it does not say new sanctions have restarted.
So do not count on this subsidy for a new godown, and do not sign a loan on the hope of AMI money. The sections below give the rules as they stood in the 2018 guidelines, the 27 Oct 2023 addendum and the 2024 letters. Use them to read an old offer or to be ready if funds return.
What subsidy rate did AMI give for a godown?
AMI gave a back-ended capital subsidy of 25% of project cost for most promoters. The rate was 33.33% for FPOs, panchayats, women, SC and ST entrepreneurs and their cooperatives, self help groups and PACS. It was also 33.33% for projects in the North East, Sikkim, Andaman and Nicobar, Lakshadweep and hilly areas. The subsidy was worked out on a cost norm per MT, not on your full bill.
The DMI letter of 4 Nov 2024 raised the PACS rate from 25% to 33.33% and doubled the cost norms. It applies to term loans sanctioned on or after 10 November 2024. The earlier norms, shown as the existing provision in that letter, were Rs 3,500 per MT up to 1,000 MT and Rs 3,000 per MT above that in general areas.
| Who | Rate | Where |
|---|---|---|
| State agencies and cooperative projects routed through NCDC | 25% (33.33% in the North East, Sikkim, A&N, Lakshadweep and hilly areas) | All States and UTs |
| FPOs, panchayats, women, SC/ST entrepreneurs or their cooperatives, SHGs, PACS | 33.33% | Areas other than NE and hills |
| All other promoters | 25% | Areas other than NE and hills |
| All other promoters | 33.33% | North East, Sikkim, A&N, Lakshadweep, hilly areas and PACS |
In the guidelines, a hilly area is a place more than 1,000 metres above sea level. SC/ST cooperatives must be certified by the State officer. If co-owners fall in different categories, the 2018 guidelines say the lower rate applies.
What cost per MT and ceilings applied?
For storage, the revised cost norm was Rs 7,000 per MT up to 1,000 MT and Rs 6,000 per MT above that in general areas. In the North East and hills it was Rs 8,000 per MT. Your subsidy is the rate times this norm, or the lower actual cost certified by a Chartered Accountant. Each category also had a top limit on tonnage and on subsidy in rupees.
The table below is from the DMI clarification of 2 Dec 2024 and applies to godowns and silos.
| Category | Rate | Cost norm per MT: first 1,000 MT / above | Subsidy per MT: first 1,000 MT / above | Max capacity | Max subsidy |
|---|---|---|---|---|---|
| State agencies and NCDC cooperative projects, NE, Sikkim, A&N, Lakshadweep, hilly areas | 33.33% | Rs 8,000 / Rs 8,000 | Rs 2,666.40 / Rs 2,666.40 | 10,000 MT | Rs 266.64 lakh |
| All other categories in NE, Sikkim, A&N, Lakshadweep, hilly areas, and PACS | 33.33% | Rs 8,000 / Rs 8,000 | Rs 2,666.40 / Rs 2,666.40 | 5,000 MT | Rs 133.32 lakh |
| Other areas: State agencies and NCDC cooperative projects | 25% | Rs 7,000 / Rs 6,000 | Rs 1,750 / Rs 1,500 | 10,000 MT | Rs 150 lakh |
| Other areas: FPOs, panchayats, women, SC/ST entrepreneurs or cooperatives, SHGs, PACS | 33.33% | Rs 7,000 / Rs 6,000 | Rs 2,333 / Rs 2,000 | 5,000 MT | Rs 100 lakh |
| Other areas: all other beneficiaries | 25% | Rs 7,000 / Rs 6,000 | Rs 1,750 / Rs 1,500 | 5,000 MT | Rs 75 lakh |
Storage of 50 MT to 5,000 MT was eligible for all promoters. State agencies and cooperative projects channelled through NCDC could go up to 10,000 MT. The 2018 guidelines also allowed silos for food grains, with ancillary facilities, up to 15,000 MT for State agencies.
PACS got one more benefit in the 4 Nov 2024 letter: a top-up for ancillary parts. These are the boundary wall, internal road, drainage, weighing, grading, packing, quality testing and fire fighting equipment. The extra subsidy is capped at one third of the permitted godown subsidy, or the actual cost, whichever is lower.
Who could apply for AMI?
Individuals, groups of farmers, FPOs and FPCs with at least 50 farmer members, partnership and proprietary firms, companies, NGOs, self help groups, cooperatives, panchayats and State agencies could apply for storage of 50 to 5,000 MT. Only State agencies, and later NCDC cooperatives, could go up to 10,000 MT. The project needed a loan from an approved lender.
The 2018 guidelines list the lenders: commercial banks, cooperative banks, regional rural banks, ADFCs, state cooperative banks, scheduled urban cooperative banks, NEDFi, and other institutions eligible for NABARD refinance. NCDC could also finance cooperative projects. Subsidy for bank projects came through NABARD and for NCDC projects through NCDC. State agencies could invest their own money and get the subsidy direct from DA&FW.
If you are still choosing a legal form, read our guide to SHG vs FPO. For loan backing for an FPO, see the FPO credit guarantee scheme.
What kind of storage counted, and what new rules came in 2023 and 2024?
Godowns, and stand-alone silos for food grains with loading, unloading and bagging facilities, counted. Railway sidings did not. Newer rules said godowns above 1,000 MT must be registered with WDRA. They also allowed one-floor multi-storey godowns up to 500 MT for non-food grain, and triangular and trapezium shaped godowns.
The DMI letter of 5 Sep 2024 gives these changes with their start dates. WDRA registration for godowns above 1,000 MT applies from 1 April 2023. Multi-storey and odd-shaped godowns apply from 8 November 2023. Renovation help applies from 1 April 2023, but only for cooperative storage routed through NCDC, at the lower of appraised cost, actual cost or Rs 750 per MT. Before that, the 2018 guidelines gave no help for renovation.
The same letter lets a promoter take AMI capital subsidy together with AIF interest subvention, from 29 September 2022. The 2018 guidelines also allowed stand-alone cold stores of up to 1,000 MT at MIDH cost norms. For that route, see our guide to cold storage subsidy.
How much did the promoter have to put in?
The 2018 guidelines asked for a promoter contribution of at least 20% of project cost and a minimum term loan, including subsidy, of 50% of cost. The 5 Sep 2024 letter cut the minimum promoter share for cooperatives, FPOs and panchayats to 10% of TFO. Their minimum term loan stayed at 50%, so the loan with subsidy could run from 50% to 90% of TFO.
Own-funded State agency projects had a promoter share of 75% or 66.67%, depending on the case, under the 2018 rules. If your own share falls below the minimum at completion, the subsidy is limited to five times your contribution, as the 2018 guidelines state. To find the rest of the money, see our guide to the Agriculture Infrastructure Fund, which explains the 3% interest subvention that can sit on the same loan.
How was the AMI subsidy paid to the borrower?
The bank gave the project cost minus your own share as loan, and the subsidy was paid to the bank in two equal parts. Half came as advance subsidy after a claim was filed online. The other half came after the bank checked the finished project and sent its report. The bank then adjusted the subsidy against your loan at the end.
The 2018 guidelines set the base rules. The whole subsidy is adjusted after the loan is repaid, but not before five years from the first disbursement, and it sits in a Subsidy Reserve Fund account in the borrower name. The DMI addendum of 27 Oct 2023, effective 1 Jan 2024, changed the steps. The bank files the claim online through the ENSURE portal within 90 days of the first loan instalment. The joint inspection by NABARD, bank and DMI was removed. The bank manager inspects the project and uploads geo-tagged photos with the final claim.
| Stage | What happens |
|---|---|
| Claim for advance subsidy | Bank files online claim with NABARD within 90 days of first loan instalment (addendum, from 1 Jan 2024) |
| Advance subsidy | 50% of eligible subsidy. NABARD releases it within 10 working days of getting funds from the Government of India, and the bank credits it to the borrower Subsidy Reserve Fund account |
| Inspection | Bank manager inspects the finished project and uploads geo-tagged photos. Joint inspection removed |
| Final subsidy | Remaining 50%. NABARD regional office sanctions within 30 days of receiving all documents |
| Delay by bank | Penal interest of 0.25% a month on the bank if the subsidy is not credited within 12 working days, and no interest on it to the borrower from the 13th working day |
| Adjustment | Against the loan at the end, not before five years from first disbursement (2018 rule) |
NCDC projects followed a similar two-step route, with the first half paid on approval and the second after inspection. Release always depended on funds from DA&FW, which is why the 2025 abeyance order matters so much.
How long did the project have to take?
After the 5 Sep 2024 revision, you had to send the project documents for final subsidy within 18 months of the first loan instalment if the TFO was up to Rs 2 crore, and within 24 months if it was larger. A 9 month extension was possible with a penalty. The penalty was 0.5% off the subsidy rate for each month or part of a month in the first 6 months of delay, then 1.0% a month for the next 3 months.
If documents were still not sent after the extension, the project could get advance subsidy only. If the project was still not complete, the advance subsidy had to be refunded at once. Here is a plain example. At a 25% rate, a project that is 2 months late loses 1.0% and gets 24%. This is arithmetic on the penalty rule, shown only as an example.
What was the overall subsidy ceiling for one promoter in a district?
A promoter who had already taken subsidy for 10,000 MT of storage in the same district in the last 10 years could not get more. Otherwise the balance was allowed up to 2025-26, with a ceiling that depended on the rate and the area. The December 2024 clarification set Rs 150 lakh at 25%, Rs 200 lakh at 33.33%, and Rs 266.64 lakh in the North East.
You had to give an undertaking that no subsidy was taken for 10,000 MT of storage in the district in the last 10 years. A different ceiling applied if you built a storage project of up to 5,000 MT and a non-storage project as separate projects in the same district. These ceilings run to 2025-26. With the scheme in abeyance, nothing is announced beyond that year.
| Case | Ceiling at 25% | Ceiling at 33.33% |
|---|---|---|
| Balance storage subsidy in a district (other than NE), within 2025-26 | Rs 150 lakh | Rs 200 lakh |
| Storage up to 5,000 MT plus a separate non-storage project (other than NE) | Rs 100 lakh | Rs 130 lakh |
| Balance storage subsidy in NE States | Not applicable | Rs 266.64 lakh |
| Storage plus separate non-storage project in NE States | Not applicable | Rs 163.32 lakh |
What would a godown subsidy look like in rupees?
Take a registered FPO in a plain area that builds a 1,000 MT godown. The cost norm is Rs 7,000 per MT, so the norm is Rs 70 lakh. At 33.33%, the subsidy is Rs 2,333 per MT, or about Rs 23.33 lakh. A trader building the same godown at 25% would get Rs 1,750 per MT, about Rs 17.50 lakh. This is an example from the official table, not a quote.
The table gives one per MT figure for the first 1,000 MT and another for tonnage above that. The clarification does not say in plain words whether the lower figure covers the whole project or only the extra tonnage. Ask your bank how it will work out the subsidy for a larger godown. The last column of the table is a cap on the total. Also, the subsidy is the lower of the norm or the actual cost certified by a Chartered Accountant. If your godown costs less than the norm, your subsidy is lower.
What about marketing projects other than storage?
AMI also supported marketing structures other than storage, such as grading, packing, e-trading and market information tools for FPOs, and primary processing units. The 2018 guidelines capped this subsidy at Rs 25 lakh for most promoters at 25% and Rs 30 lakh at 33.33%. The 2024 revision lifted a lower limit on pulse splitting and oil crushing, so those units now fall under the same Rs 25 lakh and Rs 30 lakh limits.
The 5 Sep 2024 letter added farmer-centric units such as vegetable drying, cashew roasting, jaggery making, honey processing, pulverising units for cereals and millets, and desiccated coconut units. It also allowed integrated projects of storage plus other infrastructure as a single project. For these, the 2 Dec 2024 clarification sets a maximum subsidy of Rs 75 lakh at 25% and Rs 100 lakh at 33.33%, within the overall ceilings above.
The 2018 guidelines name three other main groups. First, common facilities in market yards, such as auction platforms, weighing, drying, cleaning, grading and assaying equipment. Second, village haats and rural primary markets upgraded into Gramin Agricultural Markets (GrAMs) linked to e-NAM, a plan from the 2018-19 Budget. Third, farmer-consumer markets for direct sale to consumers and bulk buyers.
There are limits. Support structures such as parking sheds, internal roads, boundary walls and drinking water get subsidy only up to 25% of the total permissible subsidy, and a stand-alone support project gets nothing. For a processing or grading unit built in a civil structure, plant and machinery must cost more than 25% of the TFO, or the subsidy is cut in proportion.
What if my loan was sanctioned before the June 2025 order?
Your claim is on hold with everyone else. NABARD circular 149 of 10 June 2025 says the ENSURE portal was disabled for new AMI claims, and pending claims at all levels may be kept in abeyance until further orders from DMI. No page opened for this post says when these claims will be released or whether they will be paid.
Check the date of your term loan sanction. The revised guidelines of 4 Nov 2024 apply to loans sanctioned on or after 10 Nov 2024. Earlier loans follow the earlier norms. Ask your bank and the NABARD Regional Office in writing for the status of your claim, and keep a copy of the reply.
What can a farmer or FPO do now for a godown?
The Agriculture Infrastructure Fund (AIF) is the closest open route. Its Eligible Projects page lists warehouses and silos, and cold stores and cold chain. It gives 3% interest subvention a year on loans up to Rs 2 crore per project in one location. This is an interest benefit, not a capital subsidy like AMI.
The AIF Eligible Projects page and the AIF Convergence page say convergence is only for eligible projects under the AIF guidelines. The 5 Sep 2024 AMI letter already lets a promoter take both together, and lets States add a top-up. So if AMI restarts, the two can run on the same project.
- Ask your bank about an AIF loan for the godown. This is the open route today.
- If your AMI loan was sanctioned before 10 June 2025, ask the bank and the NABARD Regional Office in writing for the claim status.
- If you want to store produce and borrow against it, read the e-NWR guide on this site.
- Do not build on the hope of AMI money until DMI shows a new order.
Registration with WDRA also helps beyond AMI. A registered godown can be a base for a loan, and a place where farmers store produce and borrow against a receipt. Our guides on the Mission for Integrated Development of Horticulture and on the loan against a warehouse receipt cover two of these routes. For a longer list, see agriculture subsidy schemes and the agriculture schemes calendar.
What mistakes should I avoid with AMI?
The biggest mistake now is to build a godown counting on AMI subsidy. The scheme is in abeyance, and every release depends on funds. Other mistakes come from the rules: putting in less than the minimum own share, which cuts the subsidy base, and forgetting WDRA registration above 1,000 MT. Late final documents cost 0.5% a month. Missing the undertaking on past subsidy in the district is another one.
Two more. Do not form a co-ownership of different categories without asking the bank which rate applies. And do not trust old pages that show 25% and 33.33% without a date. Check the date of the guideline and the sanction date of your loan. Get every answer from the bank in writing, and keep your sanction letter, claim form and receipts together.
Where can I check if AMI has restarted?
Check the AMI page on the DMI website, dmi.gov.in. It holds all guideline letters and any new order. A restart would show there as a new letter after the one of 10 June 2025. You can also ask the NABARD Regional Office of your State, or NCDC if your project is a cooperative one, whether they have received a fresh budget.
Until then, treat AMI as closed to new projects and plan with AIF and your own funds. Look at the DMI page once a month. If you see a new letter, read it fully, because rates, caps and cost norms can change with it.
Conclusion
As of 24 Nov 2026, AMI is not taking new godown projects. The DA&FW order of 10 June 2025 keeps it in abeyance, and NABARD has put pending claims on hold. Learn the rules, keep your papers ready, and use the AIF interest subvention or your own funds for any godown you need now.