15 min readAs of 24 Nov 2026, NHB's notice of 8 Oct 2026 says it is not taking new Grant of Clearance applications under any NHB scheme until further orders. It is a pause, not a permanent end. A cold storage subsidy is a back-ended capital subsidy paid through your bank loan. The NHB circular of 21 Aug 2026 sets 35% in general areas and 45% in special areas, with a Rs 2 crore cap and no subsidy on land. Stores up to 5,000 MT go through your State Horticulture Mission under MIDH, whose 2025 guidelines show Rs 9,600 or Rs 12,000 per MT as the cost norm. Prepare your project report now.
What is a cold storage subsidy, and who pays it?
A cold storage subsidy is money from the Government of India that cuts the cost of building a cold store. It is credit linked and back ended. You first take a term loan from a bank. The subsidy goes to the bank and is adjusted in your loan account after the project is complete. You do not get a cheque on day one.
Two bodies handle it. The MIDH Operational Guidelines 2025 say cold stores up to 5,000 MT go through the State Horticulture Missions (the NHM and HMNEH sub-schemes). Stores above 5,000 MT are taken up by the National Horticulture Board (NHB). The same document lists NHB rates for 5,001 MT to 20,000 MT. The National Centre for Cold-chain Development (NCCD) sets the technical standards.
| Capacity of cold store | Route | Who to meet |
|---|---|---|
| Up to 5,000 MT | MIDH through NHM or HMNEH | State Horticulture Mission and District Mission Committee |
| 5,001 MT to 20,000 MT | NHB Capital Investment Subsidy (Scheme 2) | NHB, Gurugram, online portal nhb.gov.in |
| North East, 1,000 MT or more | NHB also accepts these projects | NHB (January 2025 guidelines) |
The wider mission has more parts than cold stores. Our guide to the Mission for Integrated Development of Horticulture covers them.
Is NHB taking new cold storage applications right now?
No. As of 24 Nov 2026, NHB's notice of 8 Oct 2026 says it suspends receipt of new Grant of Clearance (GoC) applications under NHB schemes until further orders. NHB says this is not a permanent end of the scheme. Applications already submitted continue to be processed. The NHB announcements page and home page (last updated 23 Nov 2026) show no later notice that lifts the pause.
Here is how it happened. The NHB circular of 3 Sep 2026 said the guidelines were revised from 21 Aug 2026. To put them in place, check pending cases and update the online system, NHB paused fresh GoC applications under Scheme 1 (commercial horticulture) and Scheme 2 (cold storage) for one month from 4 Sep 2026. The circular of 8 Oct 2026 then suspended new GoC applications under all NHB schemes until further orders. Its reason: subsidy commitments are large and the budget for the year is limited.
What can you do while it is closed? Study the rules, prepare the project report and talk to a bank. Watch the NHB website for the reopening notice. The notices name Grant of Clearance only and do not mention the optional IPA cum LoC, so ask NHB before you apply for it. The MIDH route for stores up to 5,000 MT runs through your State Horticulture Mission, and the NHB notices do not cover it. Ask your district horticulture office which rate and which application window your state uses.
What is the subsidy percentage for a cold storage in 2026?
For NHB projects, the 21 Aug 2026 circular sets credit-linked back-ended subsidy at 35% of eligible project cost in general areas and 45% in NER, Himalayan States, Scheduled Areas, Vibrant Villages, Andaman and Nicobar Islands and Lakshadweep. The maximum NHB subsidy for any type of cold storage project is Rs 2 crore.
You may see higher figures online. The January 2025 NHB guideline and the MIDH guideline of 31.12.2024 give 50% for hill and special areas. An older NHB scheme page shows 40% and 55% for stores up to 5,000 MT, and its footer says 2010. Treat both as old. The 2026 circular is the latest NHB paper on rates.
| Source and date | General area | NER, Himalayan, Scheduled and other special areas | Cap |
|---|---|---|---|
| NHB Public Circular, 21 Aug 2026 (NHB projects) | 35% | 45% | Rs 2.00 crore per project |
| MIDH Guidelines 2025, dated 31.12.2024 (up to 5,000 MT) | 35% | 50% | Cost norm per MT applies |
| NHB Guidelines January 2025 (5,001 to 20,000 MT) | 35% | 50% | Replaced by the 2026 circular |
| Old NHB web page (copyright 2010) | 40% | 55% | Old, do not use |
The MIDH guideline is dated 31 Dec 2024 and shows 35% and 50%, while the 2026 circular covers NHB schemes. So for a store of 5,000 MT or less, ask your State Horticulture Mission which rate it uses today.
Land is not part of the eligible cost under the revised NHB rules. The cap matters for big projects. At 35%, you hit the Rs 2 crore ceiling when eligible cost reaches about Rs 5.71 crore (2 crore divided by 0.35). At 45%, it happens at about Rs 4.44 crore. Spend more than that and you get no extra subsidy.
What cost per MT does the government allow?
The government does not pay a percentage on your bill alone. It sets a cost norm per metric tonne (MT) of storage. Subsidy is worked out on that norm or your actual eligible cost, whichever is lower. The MIDH 2025 norms are Rs 9,600 per MT for a civil-construction Type I store and Rs 12,000 per MT for a PEB or PEB-plus-civil store, up to 5,000 MT.
A cost norm is the upper limit of cost used for the subsidy sum. The table below comes from Annexures V and VII of the MIDH Operational Guidelines 2025. Check it against the NHB page for any change after the 2026 circular.
| Store type | Up to 5,000 MT (MIDH) | NHB: 5,001 to 6,500 MT | 6,501 to 8,000 MT | 8,001 to 10,000 MT | 10,001 to 20,000 MT |
|---|---|---|---|---|---|
| Type I (CS-1), civil | Rs 9,600 per MT | Rs 9,120 | Rs 8,640 | Rs 8,160 | Rs 4,080 |
| Type I (CS-1), civil plus PEB | Rs 12,000 per MT | Rs 11,400 | Rs 10,800 | Rs 10,200 | Rs 5,100 |
| Type II (CS-2), multi-product, PEB | Rs 12,000 per MT | Rs 11,400 | Rs 10,800 | Rs 10,200 | Rs 5,100 |
The NHB columns show per MT rates as printed in the NHB annexure of the MIDH document. The onion store (CS-1 Onion) and the dry spice and raisin store (CS-4) carry Rs 9,600 and Rs 12,000 per MT up to 5,000 MT in the same document. For CA (controlled atmosphere) add-on rates, use the NHB sheet.
Take a 2,500 MT Type II store in a general area under MIDH. This is a sample sum, not a quote. Cost norm: 2,500 MT x Rs 12,000 = Rs 3.00 crore. Subsidy at 35% = Rs 1.05 crore. In a hill or special area at 50%, it is Rs 1.50 crore. If your bank-appraised eligible cost is below Rs 3 crore, the subsidy falls with it.
Which type of cold store should I choose?
Choose the type by what you will store. NHB lists six types under the NCCD Engineering Guidelines 2025. Type I is for one product kept in bulk for a long time. Type I Onion is for onion. Type II is for many products at many temperatures. Type III is a ripening chamber. Type IV is for dry spices and raisins. A CA store is allowed only where NHB protocols exist.
These short descriptions come from the NHB January 2025 guideline, which sends you to the NCCD Guidelines 2025 for full specifications. It adds that new multi-chamber stores must be energy efficient, with insulation, humidity control, advanced cooling and automation. NHB-empanelled agencies check the technical standards.
| Type | Best for | Note from the guideline |
|---|---|---|
| CS-1 | One product, bulk, long storage | Brick and mortar, or PEB |
| CS-1 Onion | Onion storage | Special onion design |
| CS-2 | Many products and temperatures | Usually PEB. At least 6 chambers of up to 250 MT |
| CS-2 CA | CA storage of selected crops | Only where CA protocols exist |
| CS-3 | Ripening of fruit | Ripening chamber, one MT is 11 cubic metres |
| CS-4 | Dry spices and raisins | One MT is 4.0 cubic metres |
Growing onion? Our onion farming guide covers the field side. Spice growers can read about other help in the Spices Board schemes guide. To find inputs for your own crop, use the find products by crop tool.
How is storage capacity counted for subsidy?
Capacity is counted from the cooled volume. For subsidy, 3.4 cubic metres (120 cubic feet) of chamber volume equals 1 MT when you use boxes, crates or mezzanine floors. For racks and pallets it is 5.0 cubic metres (176 cubic feet) per MT. A bigger room on paper does not add subsidy tonnes unless the volume meets these factors.
The NHB guideline adds more factors, shown below. The NCCD note of 8 May 2025 repeats the rack value of 5.0 cubic metres per MT for rack and pallet chambers.
| Use | Cubic metres per 1 MT |
|---|---|
| Boxes, crates and mezzanine | 3.4 (120 cubic feet) |
| Racks, shuttle racks and pallets | 5.0 (176 cubic feet) |
| Apples in CA stores | 4.4 (155 cubic feet) |
| Dry spices and raisins | 4.0 (141 cubic feet) |
| Ripening chambers | 11 (390 cubic feet) |
Take a chamber with 6,800 cubic metres of cooled space. With crates it counts as 6,800 / 3.4 = 2,000 MT. With racks, the same room counts as 6,800 / 5.0 = 1,360 MT.
What chamber sizes and technical rules must a cold store follow?
Your project must follow the NCCD standards, or it gets no assistance. The NCCD note of 8 May 2025 sets chamber sizes. Up to 5,000 MT, each chamber is 500 MT to 1,500 MT. Between 5,001 and 10,000 MT, chambers are 1,500 MT to 2,500 MT, or any mix of the two rules. Between 10,001 and 20,000 MT, chambers are 1,500 MT to 5,000 MT.
The NCCD clarification also covers Type II stores. They need at least 6 chambers of up to 250 MT each, and you may build more. Under MIDH a Type II store up to 5,000 MT may claim subsidy on at most 20 doors. Under NHB the limit is 30 doors, for stores above 5,000 MT and up to 20,000 MT. Ante room doors are not counted.
If you plan racks and pallets, the same note gives subsidy on Rs 2,000 per MT, for up to 5,000 MT per project, at 35% in general areas and 50% in the special areas listed above. It also allows one or two sets of high-reach handling equipment. These figures are from the NCCD note of 8 May 2025, so ask NHB whether the 2026 revision changed them.
Who can apply, and who cannot?
Under MIDH, individuals, groups, firms, self help groups, FPOs, companies, corporations, cooperatives, APMCs and State Governments can get assistance for post-harvest projects. The NHB circular of 21 Aug 2026 adds limits. Only one member of a family may take NHB help, and some people, such as serving government employees, and groups of farmers, are not eligible.
The NHB circular defines family as the applicant, spouse, father, mother, sons and daughters. Once any family member has taken assistance under any NHB scheme, no other member can, even if part of the ceiling is unused. If an FPO or company has already taken assistance, its members may each apply once in their own name. A false declaration can lead to recovery with interest.
| Not eligible for NHB assistance (circular of 21 Aug 2026) |
|---|
| Present holders of constitutional posts |
| Ministers, Ministers of State, MPs, MLAs, MLCs, Mayors of municipal corporations and chairpersons of district panchayats |
| Serving employees of central or state governments, PSUs, autonomous bodies and local bodies, except MTS, Class IV and Group D staff |
| Retired pensioners getting Rs 10,000 or more a month, except MTS, Class IV and Group D staff |
| Group of farmers |
Family members of these persons may still take one-time help under the family rule. The NHB guideline of January 2025 also asks for land in the applicant's name, or a registered lease of at least 10 years. The land must be free of encumbrance, except a KCC loan. That guideline is under revision, so confirm the land terms with NHB.
Under MIDH, groups such as FPOs, cooperatives and SHGs recognised by the District Mission Committee, with at least 25 members, may take back-ended subsidy without a credit link, if they can meet their own share. An FPO that needs a loan can read how it can be backed in our guide to the FPO credit guarantee scheme.
How do I apply to NHB, step by step?
The NHB route has two letters. The In-Principal Approval cum Letter of Comfort (IPA cum LoC) is optional and helps you get a bank loan. The Grant of Clearance (GoC) is compulsory. You apply online at nhb.gov.in with a project report, land papers and the bank term loan sanction. The bank must not release the loan before GoC.
These steps follow the NHB January 2025 guideline. NHB says it is under revision, and new GoC applications are paused as of 24 Nov 2026. Read the latest notices before you act.
- Plan the project to the NCCD standards. Choose the type, chamber sizes and capacity.
- Prepare the Detailed Project Report (DPR) in the NHB template. It must be a new project, not an old activity.
- Optional, and only when NHB is taking applications: apply online for the IPA cum LoC. It is valid for 6 months, with 3 more months on good reason. You must get the loan sanction in that time.
- Take the term loan sanction and the bank appraisal note. The loan sanction date must not be more than 3 months before your online GoC application.
- When NHB reopens, apply online for GoC with the DPR, land papers, sanction letter, appraisal note and the bank cover letter with a legal search report.
- Pay the application fee online. Wait for the written GoC. Do not let the bank release the loan before it.
- Build the store within 18 months of the first loan instalment. NHB may allow 6 more months if the bank agrees the delay is genuine.
- After completion, the bank files the final subsidy claim within 3 months.
The fee changed in 2026. The circular of 21 Aug 2026 sets it by project cost, and 18% GST is extra.
| Project cost | Form and brochure fee |
|---|---|
| Up to Rs 20 lakh | Rs 2,000 |
| Above Rs 20 lakh, up to Rs 50 lakh | Rs 5,000 |
| Above Rs 50 lakh, up to Rs 100 lakh | Rs 10,000 |
| Above Rs 100 lakh, up to Rs 150 lakh | Rs 15,000 |
| Above Rs 150 lakh, up to Rs 200 lakh | Rs 20,000 |
| Above Rs 200 lakh | Rs 50,000 |
Parts that are not in the DPR and the bank appraisal note get no subsidy. Your term loan also cannot be smaller than the estimated subsidy.
How does the MIDH route work for a store of 5,000 MT or less?
For stores up to 5,000 MT you deal with your State Horticulture Mission and the District Mission Committee, not NHB. The help is credit linked and back ended, at the MIDH rate. A note in the MIDH cost-norm annexure says credit linkage may be optional for projects up to Rs 30 lakh, with subsidy paid in two instalments after a joint inspection.
The MIDH Guidelines 2025 add that public sector units, panchayats, cooperatives, registered societies, trusts and public limited companies can get subsidy without credit linkage if they meet their own share. So an FPO or society with enough own funds can take that path.
MIDH also funds smaller cold chain units. The guideline lists pre-cooling units, on-farm pack houses, mobile pre-cooling units, staging cold rooms, refrigerated vans and containers, ripening chambers and onion storage units. Annexure V has the details. A small grower may find one of these a better fit than a large store.
For help with loan interest, see our guide to the Agriculture Infrastructure Fund. The AIF Eligible Projects page lists cold stores, cold chain, warehouses and silos.
How and when is the subsidy paid?
The subsidy is paid after the project is built and the loan is fully used. The bank sends a final claim to NHB within three months of completion. A joint inspection team checks the project, and NHB approves. The money goes to the bank and sits in a Subsidy Reserve Fund Account. You do not get it as cash. The bank adjusts it only with the last loan instalment, which is not earlier than 36 months from the day the term loan was released.
The NHB guideline lists the claim papers. They include the bank letter, completion certificate, appraisal and sanction letter, date-wise loan disbursement, NOC from the state horticulture department, latest land document, a CA certificate on project cost and means of finance, and Chartered Engineer certificates for civil and mechanical work. NHB says release depends on availability of funds.
The guideline also says incomplete projects, defaults and accounts that turn NPA are not eligible, and any subsidy paid will be called back with interest. NHB added an exit rule in 2026. During the lock-in period, you may opt out by refunding the whole subsidy with any interest due. The completion limit is 18 months from the first loan instalment, plus up to 6 months.
What does modernisation of an old cold store get?
Modernisation means upgrading the refrigeration or the insulation of an existing store. For stores up to 5,000 MT, MIDH help is credit linked at 35% in general areas and 50% in special areas. The NCCD note of 8 May 2025 set caps of Rs 125 lakh for refrigeration and Rs 120 lakh for insulation on stores of that size.
The NCCD clarification also says refrigeration modernisation cannot exceed Rs 3,000 per MT of store capacity, and insulation cannot exceed Rs 1,800 per MT. A unified control system has Rs 5 lakh within the refrigeration cap. For a change of refrigerant, the cost norm is Rs 2,000 per kg for gas with a GWP of 500 to 1,000, and Rs 1,400 per kg for GWP of 1,000 to 1,500, with an upper limit of Rs 1.20 lakh and subsidy of 50% of invoice or Rs 60,000, whichever is less.
| Item (MIDH, up to 5,000 MT) | Cost cap |
|---|---|
| Refrigeration modernisation | Rs 125 lakh, and not more than Rs 3,000 per MT |
| Insulation modernisation | Rs 120 lakh, and not more than Rs 1,800 per MT |
| Unified control system | Rs 5 lakh within the refrigeration cap |
For a refrigerant change, the NCCD note asks you to show the details and capacity of the present system, its COP, the gas used, a photo of the compressor label, and a certificate from the compressor maker that the unit can run on the new gas. These figures are from May 2025, before NHB changed its rates in August 2026. For NHB projects, check the NHB sheet.
Can I use AIF together with the subsidy?
Yes, in some cases. The AIF site says the fund permits convergence with schemes such as MIDH and AMI, but only for projects, assets and beneficiaries eligible under the AIF guidelines. AIF gives 3% interest subvention a year on loans up to Rs 2 crore per project in one location. It does not replace the cold storage subsidy, and the site does not say how much can be combined.
The AIF home page states the 3% subvention, the Rs 2 crore limit and a credit guarantee for loans up to Rs 2 crore. NHB guidelines add a warning. A part that already gets help under another MIDH sub-scheme or a central scheme is not eligible for NHB assistance. So ask your bank and NHB in writing how the two will be counted before you sign.
Once the store is running, produce can be stored against a receipt. Our guide to loan against a warehouse receipt explains how an e-NWR loan works. For a plain godown, see the AMI warehouse subsidy post. It has its own status issue.
What should I check before I start a cold storage business?
Check three things before you spend. First, is there a real supply of produce in your area, and a buyer who needs storage? Second, does your design meet the NCCD standards? A store that does not will get no subsidy. Third, will a bank give you a term loan at least as large as the subsidy? Official pages give rules, not profit figures, so none are given here.
The NHB home page links to the Integrated Cold Chain Availability Platform (ICAP). Its report lists cold chain projects assisted under government schemes, state by state and by agency. Use it to see how much assisted capacity your state already has. NHB also wants a new project on land free of encumbrance, and land cost is not part of the subsidy base.
| Question to answer | Where to find it |
|---|---|
| Is there produce and a buyer in my area? | Local growers, FPOs, traders, district horticulture office |
| Which type of store suits my crop? | NCCD Engineering Guidelines 2025 and NHB guideline |
| How much assisted cold storage already exists in my state? | ICAP report on the NHB site |
| Will a bank lend, and how much? | Bank appraisal, term loan at least equal to subsidy |
| Is the scheme open today? | NHB notices and your State Horticulture Mission |
A young agriculture graduate starting an agri business can read our guide to the ACABC scheme. For a smaller business loan, see CGTMSE loans for agri MSMEs.
What mistakes lead to rejection or loss of subsidy?
The guideline points to a few clear mistakes. Releasing the loan before GoC leads to rejection. A part that is not in the DPR and bank note stays outside the subsidy. You cannot change the crop, component or bank without NHB approval. A false declaration brings recovery with interest.
- Starting work or taking loan money before the written GoC.
- Using a design that breaks the NCCD standards or chamber rules.
- Counting land cost in the project cost under the 2026 rules.
- Applying twice in one family, or hiding a family member who already took NHB help.
- Letting the account turn NPA, or leaving the project half built.
- Missing the 18 month limit, or the 3 month limit to send the final claim.
- Expecting subsidy money on a fixed date. NHB says release depends on funds.
Keep every paper in one file. Ask the bank manager early for the appraisal note, the sanction letter and the legal search report, because NHB needs them with your application.
What should I do now if I want to build a cold store?
Do the planning now, and wait for NHB to reopen before you commit money that depends on the subsidy. Read the circulars, get a DPR prepared by a qualified person, meet two banks, and ask your State Horticulture Mission about the MIDH route. Make sure your plan still works if the subsidy comes late or smaller.
Start with the NHB home page for fresh notices. Then see our agriculture schemes calendar and the wider list of agriculture subsidy schemes. If you will send produce to far markets, read about transport subsidy for farmers.
Conclusion
You can still build a cold store with government help, but the rules changed in 2026. The NHB rate is 35% or 45%, the cap is Rs 2 crore, land is not counted, and new NHB applications are paused until further orders. Read the latest NHB notice before you spend.




Leave a Comment